In the course of reading this article on contract variations and other subsequent articles that will be posted as a follow up to this, you will encounter the following terms:

The scope of works – this is the definition, statement and description of exactly and only what works is going to be performed to achieve the objectives of the project. The scope of works in a building contract is usually defined and contained in the contract documents (drawings, specifications, bills of quantities).

Variation – is any alteration to the original contract. This alteration may involve changes to the physical works or the conditions of the contract. The definition of construction changes falls under this category.

Change order – also known as a variation order. It is a written order to the contractor, signed by the owner of the building project, and is usually issued after the execution of the contract, to authorise a change in the work or adjustment in the contract or the contract sum (Al-Dubaisi, 2000, p.5). It is mainly related changes that are generated by unanticipated causes.

Building contract– this is a legally binding agreement between the contractor and the owner of the building project to execute specific works according to the contract documents in the exchange of payment of the contract sum by the owner/developer. A contract is basically a set of promises a breach of which the law provides a remedy and the performance of which the law regards as an obligation.

Contract sum – this refers to the price for the work to be executed. It is the amount of money that the employer will pay to the contractor.

Basics of Changes

Originally, when construction projects are being undertaken the aim is that they will be carried out to the final stage without having to change or fine-tune any element. The assumption for this is that all the professionals involved have done their work to completion. This is not always the case with construction as changes may be introduced here and there depending on the provisions of the contract. A construction change is introduced by the way of a change order, also known as a variation order. These changes are classified based mainly and primarily on the cause that forced them. According to (Mohammad, et al., 2010, p. 74) changes in construction are caused by design, construction, fabrication, transportation or operability. Therefore, changes can be classified into design changes, construction changes, fabrication changes, and transportation changes, among others.

Nature of Change Orders

Change orders are common to most projects and mostly very frequent with large projects. These change orders are usually related to changes that result from unanticipated causes such as changes in the scope from the owner or the developer, design changes from the architect or cost and time changes. A change order is “a document that contractually alters an original agreement between the signed parties. It is as a result of an owner approved a revision to the terms and conditions of the contract” (Long International, 2017). According to Al-Dubaisi (2000), a change order is a written order to the contractor, signed by the owner, and issued after execution of the contract, authorizing a change in the work or an adjustment in the contract sum or the contract time.

This definition is not very different from how Hollobaugh and Kearney define a variation order. To them, a change order is a written document that is signed by the owner and the contractor acknowledging the work required of the contractor and an adjustment, if any, to the agreed upon contract price or the contract schedule.

The nature of a change order can then be inferred from its cause or the reason of initiating it and the effects that they carry thereon after execution. Change orders are of two varied natures as identified by Arain and Pheng (2006) in (Mohammad, et al., 2010), namely:

Beneficial Change Orders

These are issued to improve the quality standard, reduce cost, schedule, or the degree of difficulty in a project. They serve to eliminate the unnecessary costs in a project and as a result optimise the client’s benefits and ensure value for the client’s money. Of worth noting is the fact that non-value adding costs are likely to pop out as a result of the beneficial variation orders in some circumstances.

Detrimental Change Orders

These types of change/variation orders impact negatively on the client’s value and the performance of the project. It is a compromise to the client’s value system.

Causes of Variations

There are various causes of variations; some may be foreseen while others cannot be predicted. Most authors who have written about the causes of variations seem to allude to the classification developed by Arain and Pheng (2006). This classification will then form the basis of the classification that will be adopted for the purposes of this article. They classify causes of variations/variation orders according to who initiated the changes and this gives rise to the following causes as Mohammad, et al. (2010) observes:

The client

The variations under this classification are initiated by the owner or the developer. They include the following:

  1. Change in specifications
  2. Change of scope
  3. Change of the project schedule
  4. Inadequate project objectives
  5. Owner’s financial problems and challenges

 Consultants

This happens especially when the consultants had not initially fulfilled the requirements of carrying out the project when the contract was being drawn. The architects and the engineers might not have finalised the designs and details of executing the project. The possible causes here include the following:

  1. Errors and omissions in design; mistakes made in the design
  2. Changes in overall design
  3. Design complexity
  4. Conflicts between the contract documents
  5. Lack of the consultant’s knowledge of the available design materials and methods of construction.

The contractor

In the case where the contractor has also failed to meet the requirements of the execution of the project, they may suggest some variation or changes be done. This may be as a result of the following:

  1. A situation where the contractor had not been involved in the project’s design stage
  2. Unavailability of the plant and equipment to executing the works
  3. Where the contractor has done poor workmanship as a result of erroneous construction methods and procedures
  4. Contractor’s financial problems
  5. The unavailability of manpower with the expected/ required skills to execute particular works

Other changes may be a result of causes that are not directly related to the participants in a construction project. Variations resulting from changes in government regulations, economic conditions of a country or weather changes fall under this category of causes.

Other notable authors in construction contracts and law have given the same view with regard to the causes of variations. In particular, Murdoch and Hughes (2000, p.200) identify the following three ways in which a variation can occur:

  1. Clients may change their minds about what they asked for before the work is complete.
  2. The designers may not have finished all of the design and specification work before the contract was let.
  3. Changes in legislation and other external factors may force changes upon the project team.

They advise that a clause in the contract to allow for variations should be inserted to streamline the process of making changes. However, they discourage the act of designers delaying their works until late in the project, alluding to the fact that it is bad practice and the changes clause is not meant to encourage bad professional practice among the consultants.

Effects of Variations

The maximum performance of a project can only be achieved if the works are executed strictly within the time and budget limits as contained in the contract documents. Changes in market conditions, variations in design, change of mind by the client concerning the scope of the project and other causes of variations do not allow a project to perform according to the original contract schedule. Mohammad, et al. (2010), while giving reference to other authors who have written on the subject of variations, argues that variation orders have adverse impacts on the performance of a project as they affect both productivity and the costs. The following effects of variations will be discussed here:

  1. Cost overruns
  2. Time overruns
  3. Quality degradation
  4. Health and safety
  5. Professional relations

This classification has been extensively used by other authors to discuss the impacts of variation orders on the performance of a construction project.

 

The next article will consider in detail the effects of variations in construction contracts. Keep checking this blog for updates.

 

Suggested Texts for Reading:

Al-Dubaisi, A.H. (2000) Change Orders in Construction Projects in Saudi Arabia. MS Thesis, King Fahd University of Petroleum & Minerals, Dhahran, Saudi Arabia.

Bolin, J. (2017) Effective Change Order Management. Long International, Inc. Littleton, Colorado.

Cunningham, T. (2013) Managing Post Contract Variations under the Principle “Traditional” Irish Forms of Contracts -An overview. The review presented to Dublin Institute of Technology.

Hao, Q., Shen, W., Neelamkaril, J. and Thomas, R. (2008) Change Management in Construction Projects. Presented in International Conference on Information Technology in Construction, Santiago, Chile.

Mohammad, N., Ani, C., Rakmat and Yusof, A. (2010) Investigation on the Causes of Variation Orders in the Construction of Building Project – A Study in the State of Selangor, Malaysia. Journal of Building Performance Vol. 1 Issue 1.

Murdoch, J. and Hughes, W. (2000) Construction Contracts: Law and Management, 3rd ed. Taylor and Francis, Oxford.